Daniel King
Municipal Development Services staff who presented the 2026 building code update (AO 2026-33) in March 2026.
Meetings
Sure. All right. Hello everybody. Welcome to Assembly Ordinance 2026-33. Update to title 23. That's the short title for it. I'm gonna stand back here next to the computer. Now it's pretty That was the short title. Here is our longer title. Okay this ordinance is actually going to repeal 10.75, which is fire inspection fees, those get rolled into the fire chapter of the building code. That was a request from licensing. And then it also will repeal and reenact I think 11 chapters of the building code. These are all of the building codes that get updated every three years. So it's a lot of sections that we went through in this process. The code committee meetings were set up. We had met representatives from the building board on every one of our code committees. We had over a 100 professionals in the community. That includes reviewers and inspectors from within the department, but also professional engineers, architects, contractors developers were all involved with this process. So first I want to just say thank you to the building board for your participation and all of the representatives from the community to help. This is a big big process. It was started in January of 2025 and it continued through the summer. And then in the fall, we met met with the building board twice to go over and approve all of the recommendations. We also met with the on-site tech board for some updates to the well and septic fees that we were proposing. And we're still in communication with the Alaska State fire marshal for one of the updates, which will be part of our significant changes that I will talk to you about. A little bit of background on what the committee's goals were. First and foremost, we had to be able to educate the group in these committees on what those changes are at the national level every three years. These codes and they update, they make changes with rep recommendations at the national level. We as a municipality did not adopt the interim 2021 code. So we had to be able to educate not just on changes from 2018 to 2021, but then 2021 to 2024. An example of that would be in 2018, that blue text at the top. 2018, they adopted a section on occupied roofs because a lot of people are interested in having rooftop parties. We thought we should tell people How to do that, how to handle that, because that's an added occupant load. So that became occupied roofs in the code. the national level. In 2021, they refined some of the requirements for the number of stories and the height of the buildings that could be applicable for these. And so that was an interim change that happened in 2021. And then in 2024, they changed the term from occupied roofs to occupyable roofs to try and define the difference whether your intent is that it could be occupied, that's an occupyable roof. So if you were trying to say, oh, we'll only do it in the summer, that's occupyable. Oh, we're only going to do it one month out of the year or one time out of the year, that is occupyable. And so we need to be able to capture that. This is one of those things that was really difficult to capture for the committees is to say, okay, well, this happened in 2021. We want you to know that this was an important change. And then now this other change happened in 2024. So these kind of things take a while. That is to help advise on substantial changes that can affect Anchorage, right? We need to be able to tell them all of this stuff. What we then did is discuss local issues to construction and propose and adopt local amendments for our local conditions and constraints. Things that affect Anchorage specifically what is our capabilities to regulate what is our capabilities as a very cold climate trying to deal with those issues. An example would be the code has for a long time had a section on unvented room heaters and we have historically amended out that section completely because it's not a safe condition in an area where you likely need to use this room heater six months out of the year. So we want to make sure that if you do have a room heater in the fuel gas room heater that is going to be vented to the exterior so this is an example of a local amendment that we think is important to Anchorage because of the conditions that we deal with. Other note on this update from 2018 to 2024 is we went through our insurance rating. And currently we are at a five. We were previously at a three. One would be the best you can get. And we were at a three. We are now at a five because we had not adopted the 2021 code. Once we adopt the 2024, we will be able to go back and go back to a three with ISO to work with us for this change as coming. So a note on the building safety service area for those that are or are not familiar, the building safety service area, all of Anchorage is supposed to abide by the Title 23 building codes. But we have a building safety service area that requires that you get a building permit, building plan review, and building inspection everywhere outside of this building safety service area, the blue area on the map is optional. Eagle River, Chugiak, Girdwood, all those areas don't require a building permit. They still require land use permits, but they do not require a building permit. Which was perfect fodder for a research project out of the University of Colorado Boulder and the University of Notre Dame, where they found it fascinating that we have this strong line of regulation versus non regulation, and they wanted to do research on it. What they found, they looked at the hillside on residential buildings built between 2018 and 2023 on either side of the nice straight arbitrary line line that we have for the building safety area. And they found that there was not a difference in the sale value of any of the houses in the cost per square foot. Case, but they did find that stuff within the building safety service area, the BSSA, was more complex. Usually was a larger house, more complex designs where you potentially have living over garages, more re-entering corners, which is instead of having a box, you have odd shapes sizes on your building. They posit that there is higher confidence within the building safety service area to do more interesting designs. Whereas outside of that, if you're not gonna have building review, they think that maybe you'll feel safer. Yeah, risk aversion, and you'll just build a simpler box. All right, so now we can go over some of the significant changes. I'm gonna try and just go over the highlights and if someone wants to tell me if I have got a lot of time or a little bit of time. There are more significant changes that you can see in exhibit B. But these were some of the bigger ones that I thought would be good to touch on. A significant change in the admin code is when a building permit is required. Well, one of the big changes we made was for non-structural modifications to homes. We went from a $5,000 limit to a $10,000 limit. It's been $5,000 since at least 2003. And controlling for inflation that would go up to at least $1,000 now. This is for things like repairing your roof when there's roof damage. If it's if it's under $10,000 to do it, you don't need to get a building permit. Replacing drywall, as long as it's not a firewall, you can do that without a building permit, when it's smaller areas. Yes.
And part of the challenge with that, I think is that when you remove drywall within a building, the more work you're doing, it's going to trigger the enforcement of us coming in to make sure that you're not doing something that you shouldn't, right? Under $1,000 if you're replacing a piece of drywall. We don't want you to replace firewalls without a permit. That is a life safety risk. But the smaller cost for that replacement, it allows us to try and capture when that happens. We can come in and go, okay, that actually is a section of firewall, and we do need to do something. So if it looks like a small amount of work, it's easier for enforcement. Kind of a way for us to get a handle on the scope project scope essentially.
I don't know if it's fairly common practice. We've had it since 2003. I think it was actually before when we had the uniform building code as well. Yeah, it's been in place for a long time. It allows us to capture some of this work. I'd say for like a roof, that $10,000 limit if you're replacing roof shingles a piece of the section because there was some damage. Obviously we're less concerned about that, but when you're doing a full re route, we'd have more concerns about making sure that everything gets put back correctly. We do know that replacing a section of roofing for under $5,000 doesn't always happen, right? You're not usually not gonna have to get into all of the underlayments, but just replacing the shingles alone could be $6,000 a piece of the roof. So we're trying to capture that, say, Well, we want to let you do some repairs on your house without a permit, without inspections. But not all of it. Another change in the admin code is for mobile food units and shelter units. These are two sections that that modify the requirements for the building permit. The previous version of this language was that no building permit is required. But further into the section, it says electrical permit is required, which is a building permit. So it is a little confusing, and people wanting to put in a mobile food unit get confused in the process. This also does not exempt you from a land use permit. So if you were required to, if you wanted to put in mobile food unit and you tried to just go put it in because you thought you didn't need a building permit, you it's not true. You still need an electrical permit, which is a building permit, and you still need to get land use permit, which inside the BSSA is handled as a building permit. So our proposed update to the language was that you will obtain a building permit, but you will be exempt from the building review and the building inspections, except for as listed in this language in this section, right? That clarifies that you will get a building permit. So that you do know that you have to come in here. It does not confuse people in the public when they want to put in a new mobile food unit. But it also helps them know that there is a process still that you have to go through. We saw this was a problem for one of the central Lutheran church when they were doing the first shelter units project, they came in with just electrical drawings and they were confused why they had to go through zoning because they heard that there was no building permit required, but you still have to meet zoning code requirements to put this in. So we wanted to make sure that we capture that. You will get a building permit, go through the regular process. And then the fee tables. Yes. Fee tables was another big adjustment that we made. We're proposing adding a limit to the number of inspections that can be included on commercial permits. We already have a limit on the number of inspections included with a residential permit. You get 23 inspections at a base level on a residential permit. And if you go over that amount, then you pay for those on a inspection by inspection basis. Commercial, though, if you if you spend $5,000 on your construction valuation or $1 million on your construction valuation, you get the same number of permit inspections, which is infinite. We thought that that was little much. And so what we've done is put a limit on that. We based it on the inspections that were completed on fully completed projects between 2020 and 2024. And we came up with a limit based on that. In this case, the inspection limits that we put in, 1% of permits under $1 million will go over, meaning that after $1 million of construction valuation, 1% of those permits will have inspections over the amount that they're allotted, and they'll just pay for those on an inspection by inspection basis. Between $1 million and $5 million will go over. One of the big benefits that we tried to see in this is this has allowed us to increase the number of residential inspections that we can offer. We were originally saying 23 inspections were going to be given, and then over 500,000, you would get two more for every 100,000 debt you paid. We are now just moving that to 23 inspections, and every 100,000, you are gonna get two more inspections. You'll see in the middle. Okay, you'll see in the middle. This section right here between the green and orange, those are all the inspections that will be paid for when you pay for your permit. What happens is people will come in to close out their permit and find out that they have a ton of inspections that they didn't realize that they were gonna have to pay for. All of that's now captured. So you have 15 percentage points reduction in the number of residential permits that are gonna go over when they close out their permit. So you don't have to pay a big fee at the end.
Yes. We also will be doubling the number of inspections included on retro permits. Typically it's a inspection by inspection for a retro. A retro would be replacing your water heater, extending some electrical outlet or small projects like that for a trade. And so you usually pay for every single inspection. But for a water heater, sometimes you'll get everything installed and you pay 175 for your permit fee, and then we have to come back out a second time because there's a correction. Then that just is an additional charge to the public that we don't think is necessary. So we want to make that a $350 benefit to them at $175. So you'll pay a $175 fee and you get two inspections with that. So if there is corrections, you're not gonna get charged a second time at the end of your project. We think that's a really big benefit to the homeowners, but also the contractors where it gets confusing what's paid, what's not paid. Most stuff is gonna get done in two inspections. And that's only possible by us making these other adjustments to limit other things. We can try and make it easier for more residential projects to move forward. But stop worrying. Okay, I can all right. Now to the fun stuff. Okay, our big change in the international building code is gonna be for single exit buildings. This was a proposal from the public and was considered by our architects and engineers on not only the international building code, but also the international fire code. And the discussion was to allow up to four dwelling units per floor. Current code allows you to go up to three stories tall. We are now proposing that you can go up to six stories tall and only have one exit in the building. This is the big conversation nationally, and other jurisdictions like New York and Seattle and Hawaii all have local amendments to allow similar things. And so we've been working really hard to come up with a way to do this safely, and this should really incentivise more residential construction on smaller lots to try and get more more residential units installed in town. We are seeking approval through the state since we are deferred jurisdiction, so we have a request for modification in. And we just actually had a meeting yesterday on this with the state fire marshal trying to hammer out less details. So you should expect that we will probably propose a an S version of this that's gonna include their requests. They won't approve the deferred jurisdiction request without their modification. So we're hammering that out with that to try and make it possible. And it's all to do with safety to make sure that all the right safety precautions are taken.
I can run through the rest of these. We'll have a second chance tomorrow.
Not a ton. Structurally, not a ton. What we're what we're requiring is clarifications on things like the fire alarm or smoke alarm integration. So typically on a lot of these you'll have smoke alarms in your unit, right? If you take one out, no one's gonna know until the fire inspector comes through and goes, hey, you took that out, put that back in. Now these are gonna be integrated to a fire what is the term fire alarm system. Thank you to the fire alarm system and it's monitored, it's a monitored fire alarm system. So if one gets taken out, everyone's notified that it's been taken out, right? That's not a big change. It's not a big cost increase, but it is a monitoring system. So that's a big change that we've done for that. Restrictions on the staircase itself to make sure that this is a safe space for those residents to get out, right? In the case of a fire. So there's big increases on safety for the staircase itself, but we are not proposing at this time big modifications structurally to that's gonna increase the cost. These will probably not pencil out for large lots, right? Because you have a large lot, you have plenty of space. You want to put in more than four units per floor. That's a limitation that's that's been in the base code for a long time, up to three stories. We're just saying that you can go up to six stories now. So this is for postage stamp lots that wouldn't be able to do this construction otherwise. Okay. I will run through some of these. We have horizontal wet venting and circuit venting. These are two things that we have restricted in the past for the uniform plumbing code. We are now opening the floodgates to allow this sort of stuff. Intended. Please enjoy. So that's a big good change. It allows more more autonomy to the contractors and engineers to make choices that make sense for their building. Modifation and parking space requirements. We require unit heater plugs basically at the exterior of buildings. And we have a small modification to say that up to 50% for nine plus and larger, up to 50% of the required number of outlets on the exterior can be reduced up to the number of parking spots actually provided since we no longer have parking minimums. Change in the international energy code. This is probably a big one. But it's mostly just a visual change. We are in climate zone seven, but we have historically reduced our requirements to climate zone four's standards. That would be like Seattle. We are much colder than that. And the energy code committee felt very strongly that we should be pushing for higher energy conservation on our buildings, especially our new buildings. This would be in our current construction, the R value minimum is R-21 that we put in our walls. That's a two by six wall construction with that insulation. What the code wants you to do for energy conservation is do that and then put two inches of continuous insulation on the exterior. So the code committee felt very strongly that we should be pushing for the enhanced, but it did not feel strongly enough that we should be stopping construction from happening for what you can actually build right now. So what we've done is put two columns that there is the minimum, which is the same as what we've always had, and then there's the enhanced. And this is to educate the public on if you want an energy conserving building, you should do the enhanced design, but we will approve your minimum design. So it still puts all the control into the owners of the buildings and the developers to do what they think is right, but at least tries to educate them on what is best for the community and energy. This is another significant change for the existing building code. Before 2018, we had a policy in place that required that if you had a low insulation roof and you wanted to increase the insulation, there's you're gonna be holding a lot more snow on your roof now because it's not gonna melt and drain away. So we wanted you to verify that the roof could structurally support that load. When it was adopted into the code, a subsequent AO actually modified that to say it was only applicable to buildings built before 1970. However, buildings built after 1970 often have really thin insulation, and then they come back and retrofit with thick insulation to for energy conservation. We could not enforce that you needed to get that checked. And so what we've had is people call in and say, hey, my roof is sacking after I've had this retrofit. What's the problem? And it's likely that their building was never designed to hold 40 pounds per square foot, which is our minimum design snow load. So that's holding more snow, it's deflecting more, and you can have issues. The code committee felt very strongly that we should not have this limitation at 1970. It makes sense to put that limit at the actual thickness of the insulation that you have on your roof. So we went back to what was previously there, and we added the exception for cold vented roofs, which is where there's already cold air running through your attic. If you increase insulation in that space, it helps with energy conservation, but will not drastically increase the snow load on your roof. This is an elevator one. I'm gonna just skip it for now because we can have a long conversation about it tomorrow. But there's control space issues that we feel we have a good answer for. Elevator manufacturers feel less confident that that we have an issue that they want to resolve at all, but they have not given us a cost associated with making this change. And we are supported in this change by the international union of elevator constructors, our local elevator union. So for safety reasons. And our last two items are going to be residential dwellings. There's a dwell unit separation requirement. Every unit is supposed to be fulated from the other unit with a fire separation wall. So if you have a duplex, you're going to have a one hour wall separation. This has been harder to achieve on existing buildings where you want to turn a single family home into a single family with an ADU or a duplex. And now you have to go in and retrofit in this one hour wall. There is an appendix proposed that's included in the residential code that addresses this for ADUs. And after it was recommended for adoption, what we did was subsequently turn it into an actual section in the code. We don't want to confuse what an ADU is with zoning definition of an ADU. And so we don't use the term ADU what we say is the limitations are going to be based on the dwelling size. So the proposal is if you are under 1200 square feet, if your addition is under 1200 square feet, you do not have to provide the fire separation between the two units as long as all of the smoke detectors are interconnected between the two sides. That means if there's a fire on this side the smoke detectors will go off over here. The smoke will go off over there and everyone can get out safely. If you are over that size or you don't want to interconnect them because you're you don't want to like be bothered by your neighbors cooking, then you will have to put in the fire separation because it's a risk to the lives of the people in the building. And finally, the AHBA is very happy with this option require pressure treated glulam beams or pressure treated lumber four decks We now allow them if they can protect the beam, it will not have to be pressure treated. This is supposed to be a cost savings and a timeline saver where they may not order the right lumber. And so it shows up and it's not preserved and treated. They can just put in now a regular non preservative treated lumber and paint it and cap it and ice and water shield it. Previous versions of the code have allowed just paint or stain, and then it's assume it's a maintenance item, but what we found is that you usually do not maintain it. And so you end up with these beams failing, crushing and rotting slowly over time, and it ends up being a big cost later. So this is our middle ground of protecting the tops of them and still requiring the features and hoping that they will maintain. So that was what they've cited. And that's it.
Yeah, definitely. I imagine the intent was not to undo any of that. And we got the version of the code that we started from was with from the recorders up from the from the clerk's office. Is the most up to date since we got it. We haven't had any changes to the building code specifically. There have been modifications to zoning code with relocatables, but nothing's changed in the building code with reflect to that.